With 10 A350 delivered to 3 customers as of today, the
target of delivering 15 aircraft on 2015 is more than “challenging”.
The first A350 was delivered on 2014, so there are 6 aircraft
left to be delivered in 2 months to meet the target.
This is the status of these 6 aircraft in the Final Assembly
Line at Toulouse:
Source: A380_TLS_A350
MSN13 Qatar Airways in
the Flight-line.
Test registration F-WZFH. 1st Flight 8/Oct and 3 test-flights
as of today.
Source: A380_TLS_A350
MSN19 Finnair painted with Oneworld livery. in the
Flight-line.
Test registration F-WZFN. 1st Flight 22/Oct
(unique test flight until today).
Source: Clement Alloing
MSN17 Vietnam Airlines in
the Flight-line.
Test registration F-WZFL. 1st Flight 30/Oct
(unique test flight until today).
MSN20 Finnair in the Flight-line.
Test registration F-WZFO. To be airborne in coming days.
Good luck in reaching your goal Airbus!
ReplyDeleteThis comment has been removed by the author.
ReplyDeleteLets all hope they reach their target,production next year is supposed to be at 5 per month-Qatar out of the way!
ReplyDeleteJC
A very slow start for the A350. 5U/month in 2016, well we will see. I am not that optimistic.
ReplyDeleteThe wildcard might be the two airplanes for Qatar. The last two took a long time to deliver. Hopefully those issues have been remedied.