05 October 2013

Qatar Airways CEO: “We think that the seat-mile cost efficiency of the A350-1000 will do a better job than the 787-9”



Qatar Airways is growing frustrated by the ongoing teething problems being suffered by its 787 fleet, warning Boeing that future orders could be in doubt unless remedies are quickly found.

The Doha-based airline has firm orders for 30 787s, of which 6 have been delivered, and holds 30 additional purchase rights. It aims to take all its 30 firm orders as 787-8s and is considering firming up the purchase rights as the larger -9 variant. But chief executive Akbar Al Baker says this will depend on how quickly Boeing can address the frustrations with its in-service fleet.


Qatar is closely following the A350 XWB development

The outspoken CEO, who has previously been critical of problems with the airline’s 787s, says there are “still issues and Boeing is aware of that. And they need to resolve these issues very quickly because Qatar Airways is getting very frustrated with them.”

“There are so many teething problems... although it is not anything major that would require us to ground our aircraft, it is enough to give us grief on our dispatch reliability,” says Al Baker.




Qatar Airways is considering whether to take up its 30 purchase rights as the stretch 787-9, but the ongoing 787-8 issues are playing into its -9 evaluation, which also includes the A350.

Qatar has 80 A350s on order, of which 42 are -900s and 38 -1000s. The airline is due to receive its firstA350-900 by the end of 2014.



“We will either make a decision to take the -9, or take additional A350-1000s. And we have to decide soon,” Al Baker says. “They are different sizes, but we think that the seat-mile cost efficiency of the A350-1000 will do a better job.”

The decision about which aircraft to order will be driven by “how the problems are fixed and how we are convinced that we have confidence that the problems will be fixed. With the amount of problems they’re having with the 787-8, we don’t know if this will be translated into the -9.”

Al Baker says the airline still plans to take its 30 firm orders as 787-8s, but warns that “it all depends on how much pain we are prepared to sustain”.



Based on the article “Al Baker fires off warning to Boeing about continuing 787 problems” published in Flight Global

04 October 2013

Airbus will duplícate the A350 HTP boxes assembly line in Puerto Real by 2015



Airbus approved the investment to add a new building to it´s Puerto Real site, where the A350 XWB Horizontal Tail Plane (HTP) boxes are assembled.

As confirmed by Jesús López Medina, Airbus Puerto Real Director, the factory will be expanded with a building of around 3,000 square meters.


click the picture to watch a video

Jesús López Medina explained that the A330 assembly line will be moved to the new building, allowing the duplication of the current A350 HTP boxes assembly line. In Puerto Real site, Airbus also assemblies some workpackeges for the A380.


The duplicated line for the A350 assembly need to be setup for the beginning of 2015.

For the head of Airbus in Puerto Real, "this decision is important; Airbus has seen that it is something necessary, that these components are not going to be subcontracted”



“This year we will be delivering to Getafe site between 8 and 9 aircraft, but the coming year we have to deliver the double. We have to expand the factory because the production of the A350 is growing. This year, at the Puerto Real plant we have allocated between 25 and 30 people, of these, 18 are operators and 5 design engineers. The plant not only wins in workload with white collars, but we provide autonomy to solve needs to make modifications in drawings, etc., without having to go to Madrid. The Airbus management gives autonomy to this factory, which is a qualitative growth".



Based on the article “Airbus ampliará su planta de Puerto Real para asumir el A350 y el A330” published in Diario de Cádiz.

03 October 2013

First VMU test could be completed last week in an airport close to Paris.


The first VMU test could be performed last 26/Sep in an airport around 30 km south or southeast of Paris. It could be at Brétigny sur Orge (LFPY) or at Melun Villaroche Aerodrome (LFPM).

The A350 first prototype MSN1 took off from Toulouse at 04:28 UTC early in the morning (06:28h local time) as AIB57WB after 4 days of no test-flights, used in the Flight Line to prepare all the special equipment required for the VMU test. The aircraft landed back in Toulouse 6 hours later at 10:14 UTC (12:14h local time).


Brétigny-sur-Orge Air Base

Brétigny-sur-Orge Air Base (LFPY) is a French Air Force base. The base is located approximately 17 miles (27 km) south of Paris. Today, the base is a modern, fully equipped NATO base. The base has a new 3km runway recently marked with an excellent concrete surface.



Melun Villaroche Aerodrome

Another possibility is the Melun Villaroche Aerodrome that is located in the Île-de-France region in north-central France. The airport has two paved runways: 10/28 measuring 1,975 by 45 metres (6,480 ft × 148 ft) and 01/19 measuring 1,300 by 30 metres (4,265 ft × 98 ft).

The Bureau d'Enquêtes et d'Analyses pour la Sécurité de l'Aviation Civile, the French air accident investigation agency, has facilities at Melun Aerodrome.

flying on 26/Sep/2013



SNECMA (SAFRAN) has a large manufacturing plant to the south of the airport.

This aerodrome is best known for the numerous tests of aircraft prototypes that have occurred until the early 1980s, especially those of several military aircraft such as the Dassault Mystery; Mirage, and VTOL designs. It was also a test center for SNECMA.

Many World War II relics can be found at the airport, abandoned taxiways with aircraft hardstands are evident with deteriorating concrete. A munitions storage area remains to the east of the north-south runways in a wooded area along with what appear to be old concrete hangar foundations, buildings, and other wartime concrete taxiways.




In few days we will know where the tests were done, with spectacular pictures taken by Airbus.

02 October 2013

Design of the engine for A350-1000 on track. Drawings release & parts manufacturing phase starts after CDR maturity gate passed by Rolls-Royce.


Rolls-Royce and Airbus have completed a critical design review (CDR) for the Trent XWB-97 engine destined for the A350-1000.
The XWB-97 is designed to generate the higher thrust needed by the A350-1000 without any increases to the size of the nacelle used on the A350-800/900, and without impacting the specific fuel consumption or on-wing life of the engine. To solve this conundrum, the larger engine incorporates a higher flow-capacity fan to pump more air, a larger core to increase flow and higher-capability turbines to extract power for the fan.

Prototype demonstrations to prove key technology for these improvements also are underway at INTA (the Spanish space agency) in Spain, using a modified XWB-84, and the design groups at the CDR meeting viewed data from these tests as part of development review.



“Some key milestones are coming,” says Trent XWB’s program director Chris Young. Development activity is rapidly accelerating on the new engine as the first Trent XWB continues in flight testing. “We still have a lot of people working on the 84K [XWB-84], but now we have passed the crossover point where there are more people working on the XWB-97.”

Prior to the joint review with Airbus last week, R-R had “just completed the CDR for the 97K engine. It’s a really important milestone because it is the one that says you are good to start machining and to start releasing the drawings to get into final manufacturing. After that is when parts start coming in to stores at the end of the year and early next year. That clears the way for the start of assembly and first test in the middle of next year,” Young explains.



Following the completion of a PDR-preliminary design review for the XWB-97 in January, Young says “there is real raw material coming together for forgings and castings.” These include the completion of rough machining of the first variable stator vanes, initial machining of the intermediate pressure (IP) compressor sixth-stage disc, and trials of the linear friction stir weld process on the IP compressor first-stage blisk. The cone for stage six of the high-pressure (HP) compressor rear drum assembly and other core parts of the first engine are also underway.

Baseline development engine ESN20001 has begun runs of XWB-97 development materials and tip clearance control systems. Tests will evaluate new shroudless HP turbine blades and seal segments. “So we are trying to prove that when the turbine runs into the ceramic seal it will last forever, even though it has had a rub,” says Young.
A second run early in 2014 will include tests of a “full standard of shroudless turbine with tip clearance and cooling,” he adds.

The engine is scheduled to be flight-tested on the Airbus A380 flying testbed at the end of 2015, and will power the A350-1000 for its maiden flight in 2016. Entry-into-service is targeted for mid-2017. Meanwhile, the XWB-84 version continues in flight test on the A350-900 prototype, which it has powered without incident since the first flight on June 14.



Based on the article “Rolls-Royce Reaches Critical Design Review Milestone For A350-1000 Engine” published in Aviation Daily

01 October 2013

Airbus and Boeing have similar joint ventures in China with the same company AVIC to manufacture composite parts for A350 and for all Boeing models.



Airbus is looking to deepen its ties with China despite wider industry concerns surrounding technology transfer to the emerging aerospace power.

Chinese production of components for the A350 is already under way at the Harbin Composite Manufacturing Centre (HMC), a joint venture between Airbus (20%) and local partners (80%).



First elevators manufacturing is on progress in HMC and it aims to be the sole producer of rudders, section 19 maintenance doors and belly fairing parts for the A350 by 2017.

Jose Antonio Veroz, the plant´s general manager, says that there are no plans to increase the list of A350 parts made at the site. “There is no additional workload of the A350 planned for China now” he says, noting that the facility is specifically sized to cope with the production demands of the new widebody.



Although he concedes that costs of Harbin will initially be higher than elsewhere, these should decrease as the facility becomes more efficient. Airbus´s business case “is not built in the short term”, he says.

Airbus has stipulated that the factory can only carry out work for its programs. However, this restriction may be loosened if opportunities become available. “In the future if it´s beneficial to us and our partners and it makes commercial sense to develop parts for other manufacturers, including Comac, there is a possibility” says HMC´s head of international co-operation Gao Zheng.




Airbus China COO González Ripoll adds: “Airbus is in China to stay. Our wish is to have long-term partnerships with the Chinese. We are looking for such opportunities”







Boeing Tianjin Composite joint venture with AVIC, located in Tianjin, has 1000 employees and manufactures interior parts and composite structures. 737 horizontal stabilizers are also manufactured and assembled in China (by SAMC) in a 10-year contract until 2021.



Boeing has no intention of setting up a final assembly line in China –as Airbus has done in Tianjin for A320- according to Boeing China president Marc Allen. “We´re not going to do a me-too!” he says, even if there is a need to ramp up production rates in the future. “Will we do a big thing here in the future? Yes, absolutely. But not that.”

“We will help Chinese suppliers expand through raising their capabilities. That way, if we up our production rates, the impact reaches right into China”.



Boeing is the world´s largest purchaser of aerospace components out of China ($1,5 billion in hardware and services since 1980). Chinese components are flying on 7000 Boeing airliners worldwide.



Based on the article “Airbus seeks to bolster Chinese links” published in FlightGlobal and based on the article “Boeing- No final assembly in China” published in ShowNews – Aviation Now.

30 September 2013

Starting with A350 XWB program, “we broke with previous decades’ practice of work-share being assigned according to an artificial kind of national split” T.Enders EADS CEO.



Airbus said it won’t return to a previous practice of apportioning work on new programs by national ownership structure, adding to signs that the European manufacturer is emancipating itself from political meddling.

Airbus first dropped the practice on its A350 wide-body jet, where the fact that France got more work so riled the German government that it continues to withhold some financial aid. Even so, the Toulouse, France-based company will continue in its new vein, said Tom Enders, the CEO of Airbus parent EADS.



“We broke with previous decades’ practice of work-share being assigned according to an artificial kind of national split,” Enders told journalists in Paris. “It was the first program where we looked at what is the best, most competitive supplier, and that’s certainly something we’ll insist on going forward.”

The comment highlights a liberation from government ties that Enders, a German and vocal critic of political involvement in his company has sought to push through. Airbus contributes 80 percent of revenue to the parent company, and Enders sought to balance out civil and defense sales last year with a merger with BAE Systems, which failed because of opposition from Germany´s government.




Germany has complained that Airbus’s factories there were given less work than those in France on the A350 XWB jet.

Germany has pledged 1.1 billion euros ($1.56 billion) toward the A350, or 1/3 of the contribution made together with France and the U.K. The A350’s development costs amount to about 11 billion euros.



EADS, also based in Toulouse, has overhauled its shareholder structure since the collapse of the BAE discussions late last year. Germany, which previously held no direct stake in the company, gained a 12 percent to match France’s reduced holding.

At the same time, governments no longer have the special veto rights that they possessed under the old structure.




Based on the article “Airbus Throws Out Workshare Rule as Government Involvement Wanes” published in Bloomberg

29 September 2013

Nose landing gear doors for the A350 XWB are made in Corsica; French Minister for Foreign Trade visits CCA in Ajaccio.


Last week, the French Minister for Foreign Trade Nicole Bricq visited Corse Composites Aeronautique (CCA).



CCA is a company with 250 employees whose turnover is around EUR 40 million. It is located in the industrial area of the Vazzio in Ajaccio. The 4 shareholders of the company are Airbus with 25.6% and Dassault, Safran and Latecoere with 24.8% each.



CCA is focuses on 3 main product families: nose landing gear doors, karmans and barrels for engine nacelles.


It was founded in 1983 as a manufacturer, in 1993 was a build to print company and 10 years later in 2003 a risk sharing partner, increasing responsibilities on the work packages and programs involved.






Based on the article “Nicole Bricq visite l'entreprise Corse Composites Aéronautiques” published in Corse Net Infos